Strive to complete Trung Quan Bridge in first quarter of 2014

(Quang Binh Website) - Chairman of the provincial People's Committee Nguyen Huu Hoai and his delegation on October 25 went on an inspection tour about the implementation progress of Trung Quan Bridge in Quang Ninh district.

Inspecting Trung Quan Bridge

The project was begun construction on August 17, 2010 with a total investment of 125 billion VND. So far, the project has completed 76% volume of work, approximately 95 billion VND out of 125 billion VND.

After the inspection tour, Chairman Nguyen Huu Hoai praised the executive unit for its efforts to overcome difficulties to ensure the project implementation progress. Chairman Hoai also asked the investor and contractor as well as relevant agencies to mobilize all resources and create all favorable conditions to speed up the project implementation progress with a high quality, striving to complete the project in the first quarter of 2014 to welcome the 410th anniversary of establishment of Quang Binh province.

Reported by Dang Ha