Permanent Vice Chairman Nguyen Xuan Quang inspects the implementation of the Van Hoa Cement Plant Project

(Quang Binh Website) - On Feb 23, Permanent Vice Chairman of the Provincial People’s Committee Nguyen Xuan Quang made an inspection tour about the implementation of the Van Hoa Cement Plant Project.

Van Hoa Cement Plant is invested by the Vietnam Construction Materials Company.,Ltd with a total investment of VND3,941 billion. The plant has a capacity of 2.2 million tons clinker a year. So far, the plant has completed 60% of workload.

It is expected that the plant will carry out a trial run in the first quarter and hand over in the second quarter of 2013.

Permanent Vice Chairman of the Provincial People’s Committee inspects the project

During his trip, Permanent Vice Chairman appreciated the efforts of the contractor and local authorities in implementing the Van Hoa Cement Plant Project and shared difficulties in capital and site clearance with the investor.

He stressed that relevant agencies and localities should create favorable conditions and closely coordinate with the investors to solve difficulties and put the plant into operation as scheduled plan.