Chi tiết tin - Quang Tri Portal
30 communes invested to rehabilitate and expand rural grid system
(Quang Binh Website) - The Second Rural Energy Project (RE II) has invested VND113 billion to rehabilitate, upgrade and expand low voltage network for 30 communes of 5 districts of Quang Binh province. Of which, Le Thuy has 7 communes, Quang Ninh 7 communes, Bo Trach 5 communes, Quang Trach 8 communes and Tuyen Hoa 3 communes.
Among 462 km of low voltage network invested by the project, 264 km has been built newly; 198 km upgraded and repaired; 24,671 watt-hour meters installed (of which 6,573 meters were installed newly and 18,098 replaced newly). Project duration has been implemented in the period 2007 to 2010. After completion, the rural grid system will be handed over the collectives to manage and use.
Reported by QB Newspaper No.211 - Translated by N.Y
More
- Export turnover in nine months achieved 90.5% of plan (20/10/2008)
- ''Companion in arms'' study encouragement scholarship awarded (20/10/2008)
- Bo Trach district: more than 60 capital construction projects to be operational (20/10/2008)
- Viettel Corporation donates VND100 million to help Quang Binh province overcome damages caused by Storm No.7 (17/10/2008)
- Quang Binh University held an opening ceremony for new academic year of 2008-2009 (16/10/2008)
- Dong Hoi City People's Committee reports plan of 2009 (16/10/2008)
- Senior delegation of Quang Binh province paid a visit and had a working session with provinces of Khammouane, Savannakhet and Champasac (Laos) (14/10/2008)
- Sum up partially three-year implementation of Decision of Prime Minister on building and improving quality of teachers and education managers (14/10/2008)
- Provincial Standing People's Council held a joint sitting to prepare contents and agenda for the 14th session of the 15th Provincial People's Council (13/10/2008)
- Quang Ninh district invests VND1,133,360,000 to build district's children house (09/10/2008)